HOW THE GREAT SOUTHERN TRAIL GREENWAY MORPHED INTO A “WORKING FARMYARD” AT COOLYBROWN, ARDAGH, CO LIMERICK

Liam O’Mahony from the Great Southern Trail Greenway has sent us the following update explaining how the GST Greenway has morphed from a greenway to a ‘working farmyard’ at Coolybrown, Ardagh, County Limerick – and how this is at odds with maintaining the integrity of the publicly owned route.

The directors of the Great Southern Trail Ltd. (GST) have discussed the recent announcement by Limerick City and County Council (LCCC) of a €5 million upgrade for the Greenway and wish to draw public attention to the history of the “Coolybrown working farm” element of the otherwise broadly welcome proposals:

This story begins in 2003 with a successful planning application for a 180 square metre slatted unit to be constructed in a Coolybrown farm to the south of the railway. The application was revised in 2006 to double the size of the unit and this was also approved. 

In the interim the adjacent old Limerick to Tralee railway corridor had its right of way protected by the Mid-West Regional Authority for recreational and environmental pursuits in 2004.

Therefore, in 2007, when another incarnation of the yet unbuilt slatted unit manifested itself in planning application (07/1592) Limerick County Council, referencing the Regional Authority guidelines, wrote to the applicant on 20 July that it was “not favourly disposed” to the application and advised that it should be relocated to the northern side of the railway where the bulk of the farmlands and buildings were located. The Council requested further information. Surprisingly, having received no new information or proposals (only a regurgitation of the previous 2003 and 2006 files (received on 30 July), the Council approved the application on the following day, 31 July 2007.

These events all pre-dated the 2010 development of the Rathkeale-Ardagh section of the Greenway; all of which works were  undertaken by the GST. It was only then that it came to light that the plans approved three years earlier for (07/1592) had not been complied with. The slatted unit was now several metres closer to the railway than the planning permission permitted. In fact the cattle were being fed on the CIÉ railway property.

It was most surprising to the GST that Limerick County Council hadn’t apparently checked over the intervening three years to see that the structure had been built in accordance with the planning permission. The unauthorised slatted unit also received grant-aid from public funds; a matter which again merits investigation.

With the opening of the Rathkeale-Ardagh section by the GST the regulation of the situation in Coolybrown was an imperative. The landowner applied for retention under new conditions. It was to be hoped that the decision on this application (12/222) would bring closure to the saga and satisfy all the parties. The permission was granted but conformity with the conditions by the applicant and enforcement of them by the Council has unfortunately been less than satisfactory. 

That’s the story of the southside of the railway and now we proceed to the northside. CIÉ, being the owners of the railway route, have compounded the “working farm” scenario. They chose to split the railway corridor in half over a length of several hundred metres on the northside of the track in the Rathkeale direction. This was to facilitate the same landowner with direct and easy access to some external lands that he was renting. This more than generous decision of CIÉ in the early months of 2011 was as a result of representations made by a third party (whose name is known to the GST) directly to the then Chairman of CIÉ, Dr. John Lynch (recently deceased).

The overall result of the CIÉ and LCCC indulgence is that non local users of the Greenway when encountering a narrowing of the railway route and its less than attractive appearance, to their left and to their right, actually believe that they are in a farmyard.

To compound all of the above the  LCCC current plan to use public funds and to detour away from the railway for a length of 800 metres is the final capitulation. It is also a recipe for similar demands on sections yet to be developed.

During the GST twenty-five years of campaigning, developing and managing the Greenway we never entertained requests to deviate from the railway corridor. We viewed it as land held in trust by CIÉ for the people of Ireland.

Our hope now is that wiser council will prevail with this ill-advised current proposal being further investigated and resolved in the public interest.

The GST Greenway has the capacity to be a world class facility and of major benefit to locals and visitors alike. The integrity of the entire way without any proposed private diversion is a key element of the facility now and for future generations.

One thought on “HOW THE GREAT SOUTHERN TRAIL GREENWAY MORPHED INTO A “WORKING FARMYARD” AT COOLYBROWN, ARDAGH, CO LIMERICK”

  1. This sounds very like the insanity on the great western cycleway where it appears somebody (probably the council )built what looks like a water treatment plant forcing the cycleway to leave the trackbed and climb a long steep hill only to come down the other side and rejoin the way when a slight swerve could have done. There seems to be a lot of clorine gas on site which may explain the large diversion.

Leave a Reply

Your email address will not be published. Required fields are marked *